– project 75% completed, on track for March 2025 completion
Work on the new US$260 million bridge across the Demerara River is advancing with the installation of the first precast girder on Friday, marking a milestone stage of the project. The precast girder is a horizontal steel beam that will support the deck of the bridge and the weight of traffic.
Engineer at the Public Works Ministry, Patrick Thompson, who is overseeing the bridge project, explained that a total of 472 girders have to be installed with each set of piers having eight girders connected to each other.
“The girder is then going to be connected to the girder launcher (a crane) and it’s going to be launched onto the first two piers… When this process is completed for the first eight girders, the launcher will be moved successively and so we will continue to launch all the girders until we get to the central span of the bridge,” he noted
These girders, each measuring 42 metres and weighing 120 tonnes, are being installed simultaneously at both ends of the bridge using the launching crane that was custom-built in China for this project.

“If the process were to continue simultaneously, it would probably take a day to launch all eight girders. The traveller has to move back and forth, and the traveller moves less than two kilometres per hour, which is less than your walking speed,” the Ministry engineer stated.
The construction of the new Demerara River Bridge is being executed by China Railway Construction Corporation Limited (CRCCL).
According to Thompson, works on the bridge structure are about 60 per cent completed while the overall project is about 75 per cent complete.
Public Works Minister, Juan Edghill, who was present to witness the girder installed on the western end of the bridge, assured that the project is on track to meet the March 2025 deadline.
“That is the deadline we’re working towards… The operation here at the bridge is a 24-hour operation… The progress has been continuous. I do get weekly reports and we are on track… So, we are moving along,” Edghill said.
The Public Works Minister further stated that the only thing that could cause a delay in this project is the workers not moving at the pace that they should
“But I think the company is adequately mobilised and the machinery is there,” he stated.
By the end of December, the towers that will hold the highest span of the bridge should be elevated to peak at 112 metres high. Currently, those two towers are at 73 metres.












