– installation of transformers to begin by this year end

The 2024 Mid-Year report has revealed that during the first half of the year, $40.8 Billion was spent to advance work on the transformational Gas-to-Energy (GtE) project, which will provide an additional 300 Megawatts (MW) of power to the grid when it comes on stream next year.
The report states that the GtE is progressing steadily. It was pointed out that $40.8 billion was spent to advance works that included the installation of 9,018 of 9,614 joints of a deepwater natural gas pipeline.
“The pipeline is on schedule to be completed by the end of 2024, with the hook-up to the station expected in the first half of 2025. Further, the material offloading facility is now utilised while piling has started for the commencement of the foundation activities… works were completed on 114 of the 371 pole foundations for the installation of transmission lines,” the report states.








