Sussex St bond scandal
…paid $337.5M to Larry Singh in 2 years
…criminal probe, disciplinary actions recommended
Following a special audit into the Sussex Street, Georgetown bond scandal, the Audit Office of Guyana has found that there were clear breaches of the Procurement Act and recommended that the Police be called in and the Legal Affairs Ministry take disciplinary steps where necessary.

According to the report on the special audit produced by Auditor General Deodat Sharma and addressed to Attorney General and Senior Counsel Anil Nandlall, the contract for a medical storage bond was not advertised or publicly procured by the former A Partnership for National Unity/Alliance For Change (APNU/AFC) Government. This is a breach of Tender Board procedures and the Procurement Act of 2003.
The then Public Health Ministry had always claimed that they rented the bond from Linden Holdings Inc because it was needed on an emergency basis. However, the Audit Office found that despite $25 million being paid for the first two months the bond was rented (July and August 2016), the bond was not used until the third month.
Another issue is the fact that the bond was underutilised and under-equipped, despite contractual stipulations. For instance, the contract mandated that the building would be equipped with 16 upright refrigerators. But at the time of physical verification on April 11, 2017, only 14 were seen.
“The contract stipulated that there should be central air condition on both levels and back up of twelve 18,000 BTU air conditioning units. However physical verification revealed that ten of the units were 18,000 BTU, while two were 12,000 BTU,” the AG also found.

Additionally, physical verification done by the Audit Office in 2017 found that the bond contained only 472 IUD kits and associated supplies and 1200 umbilical cord clamps. In addition, there were 2130 amphotericin 50mg injections and 8300 condoms.
Contract
There is also uncertainty about the date the contract actually ended. The contract was supposed to last from June 1, 2016, to until June 30, 2019. In accordance with the need for one-year notice, then Permanent Secretary of the Ministry of Public Health, Trevor Thomas had sent an initial Notice of Quit letter dated October 31, 2016, informing Linden Holdings of the intention to vacate the premises by November 1, 2017.
“However, examination of this letter revealed that it was unsigned and issued without the official letterhead of the Ministry. Evidence was seen whereby someone would have signed a Document Transmission Slip on 8 November 2016 receiving the Notice to Quit,” the AG said.













