After almost 5 years in office
After almost five years in Government, the Public Infrastructure Ministry has only been able to install solar panels and energy-efficient lights, while a number of major projects that Government had announced would lead to renewable energy remain unfinished, even as elections and the end of a term in office draws closer.
The Public Infrastructure Ministry held a press conference on Wednesday, where an account was given for the Ministry’s performance for last year. When it comes to energy, Public Infrastructure Minister David Patterson announced that they installed 81 solar panels on Government buildings for 2019.

He also noted that at a cost of $165 million, over 20,000 energy-efficient lights were changed in the hinterland. But projects such as the Hope wind farm, the Kato hydropower project, and the Mabaruma solar farm remain in the works.
The Mabaruma solar farm project, according to the Minister, is presently still at the tendering phase for certain components. Patterson was, nevertheless, optimistic that the project would be completed by next month.
“The panels are installed… we have a series of panels on posts on the ground. They take over an area of about an acre. The rumour on the ground of it being taken over by bush was a question of the guys not weeding it… that has been taken care of. That’s (not what’s) wrong with them, the solar panels have a lifespan of 25 years.”

“The issue with the operation of the whole system is the panels, the software, battery and inverters. The issue was the batteries and inverters were incorrectly installed. So those are the new ones that are out to tender and will be installed… the tender was out two months ago… it’s supposed to be finished before (February 23).”
In the case of the wind farm, Patterson explained that all the technical aspects are supposed to have been completed. He noted that the project is now a matter for the developer and his financing. Other projects are also in the pipeline.
Some are being carried out by the Guyana Energy Agency (GEA), while others are being overseen by the Hinterland Electrification Company Incorporated (HECI). Both come under the jurisdiction of the Public Infrastructure Ministry.
“The GEA has identified seven potential sites located along the Guyana coast to conduct detailed wind resource assessments, to develop utility-scale grid-connected wind farms. And we’re monitoring them as we speak now. We need a year’s data, and with that data, we will invite persons to bid or develop projects to harness the wind energy,” he said.