Demerara Harbour Bridge to undergo major maintenance works
The Demerara Harbour Bridge will again undertake substantial maintenance works similar in nature to those it had undergone earlier in the year. This time, work will be done to the eastern half in the third quarter of 2016.
These works will be done to the retractor span, which allows large marine vessels to go up and down the river, and will last four to five
days.
The extra-large pontoons at the retractor span will be replaced. This will result in the bridge being closed to marine traffic for that period.
Demerara Harbour Bridge Corporation (DHBC) General Manager Rawlston Adams told the Government Information Agency (GINA): “Only one half of the bridge will be opened to allow large vessels to pass.”
“We’re awaiting the delivery of a second pontoon to do exactly the same work on the western end of the bridge so once the pontoon is delivered, which should be some time in the third quarter in the year, we will execute that work,” Adams said.
The sum of $150 million will be spent on the bridge for continued maintenance this year.
On July 8, the DHBC received Cabinet’s approval for $51 million to be spent to rehabilitate pontoons and fabricate buoys, Adams noted. “We are currently awaiting approval from the National Procurement and Tender Administration Board to forward to Cabinet for us to start other works.”
Additionally, Adams pointed out that there continued to be an increase in traffic on the bridge which would not change, “until something more happens in terms of building … another bridge”.
He further explained that as the economy grows, more persons are relocating to Region Three. “They buy /import new vehicles, increasing traffic, and that poses a challenge to us with respect to traffic management.”
However, the Corporation’s approach to managing the increased traffic is to engage the Guyana Police Force for its assistance in traffic management, getting timely information to the public and asking commuters to try as much as possible to be on time before the bridge retractions.
In April 2016, the DHBC was closed for six hours, for maintenance works on a pontoon which had to be changed as part of a menu of works that has to be completed during the course of this year.
The bridge is a vital link for commuters between Regions Three (Essequibo Islands-West Demerara) and Four (Demerara-Mahaica).