ENVIRONMENTAL AUTHORISATION PART 2

Last week, we took a brief look at Environmental Authorisations (EA) granted by the EPA in Guyana. It was noted that EAs are necessary for the protection of human health and the environment, as they identify potential pollution sources and mitigation measures before development activities occur.
Additionally, having an EA is beneficial to the developer, as it is a legal requirement, and saves time and money in the long term, as conflicts with other stakeholders are addressed before significant financial investments are made.
After an application has been received, it is ‘screened’ to determine whether or not an Environmental Impact Assessment (EIA) is required.

EIA not required
Once it is determined that an EIA is not required, the EPA would publish a notice to the public, in at least one daily newspaper, informing of the EPA’s position, and thereby allowing public input into the decision-making process.
An appeal against the Agency’s decision may be made to the Environmental Assessment Board (EAB) within 30 days of the publication of the notice. Once there is no objection, an Environmental Permit is issued, with conditions for environmental management, against which developers are to report when submitting an annual return to the EPA. Additionally, for some projects, an Environmental Management Plan (EMP) may be required in order to detail measures to mitigate known/potential environmental impacts.

EIA required
If an EIA is required, the developer would be requested to select qualified persons to undertake the study. Once the team of consultants has been approved, and a draft Terms of Reference (TOR) prepared, the Agency would publish, in at least one daily newspaper, a notice of the project, inviting public submissions on issues or areas of concern that should be addressed in the EIA. The TOR for the EIA scope of work would determine the nature and extent to which the consultants would examine issues of importance which emerge during the scoping exercises. The consultants would conduct scoping of the project during the active public consultations facilitated by the EPA. The scoping exercises would identify what possible impacts there may be from the project and from alternatives considered. It is during the scoping process that important environmental components likely to be affected (air quality, water quality, biodiversity etc.) are identified, along with potential issues of conflict between stakeholders.
The EIA has three (3) components: an Environmental Baseline Study, an Environmental Assessment, and an Environmental Impact Statement (EIS). Once the EIA study has been completed and the report prepared, the developer would submit, at a minimum, eight (8) hard copies and one (1) electronic copy of the EIA, which must include the EIS. The EPA would publish a notice, in at least one daily newspaper, notifying the public of the submission of the EIA. The public would have sixty (60) days from the publication date of that notice to make submission to the EPA and/or EAB. The EPA, along with the sector agency, would review the EIA. Whilst reviewing the EIA, the sectoral agencies would also ensure that the EIA is consistent with any plan, guideline, regulation or code of practice developed by them. Copies of the EIA and the findings of the review by the EPA and sectoral agency would be passed to the EAB for review and recommendation.
The Environmental Assessment Board (EAB) would advise the EPA whether the EIA is acceptable, and the conditions to be attached to the Environmental Permit should it be granted. Should there be need for additional information before a decision is made, the developer would be requested to submit such information. A new draft of the EIA, or an addendum if the comments are not significant, should then be prepared by the consultant, and must address the comments of the EPA, the sectoral agency, the public, and the EAB. It is essential that the consultants clearly indicate how each comment has to be addressed.
The EPA would take into account the EAB’s recommendations, the sectoral agency’s recommendations, the public’s comments and the EPA’s own review and decide whether or not the project should be approved. For the approval project, the EPA would issue an Environmental Permit with the terms and conditions necessary to effectively manage the environment, and in accordance with the prescribed fee. Should an Environmental Permit not be granted, the developer may, within fourteen (14) days, file an appeal with the Environmental Appeals Tribunal (EAT).
Ensure that you submit your application for Environmental Authorisation; and remember, the environment is everybody’s business!