Works are progressing steadily on the highly anticipated four-lane highway stretching from Diamond to Buzz Bee Dam, East Bank Demerara (EBD), with an official deadline set for March 24, 2025.
President Dr Irfaan Ali inspected the ongoing construction on Thursday, as efforts ramp up to complete the third phase of the Government’s massive road expansion initiative. According to the contractor, 61 per cent of the project is already completed, with drainage works reaching 80 per cent completion, while road works on both the northern and southern carriageways are currently at 36 percent. To meet the deadline, night works have also commenced.
The head of state has warned the contractor against not complying with the stipulated deadline and contractual specifications.
“We’ve got to make sure that by March 31st, that’s the Buzz Bee Dam section is complete because there’s no extension here. We have to get this completed and you can’t have the contractors going to the Land of Canaan, they can’t be breaking up that access,” the Guyanese Leader said.