
The contractors working on the $11.8 billion four-lane highway project from Schoonord to Crane in Region Three (Essequibo Islands-West Demerara) are expected to pay liquidated damages over the delayed completion of the road.
During a recent inspection of the ongoing works, President Dr Irfaan Ali was informed that the works are about 90 to 95 per cent completed at the two sections – Schoonord, West Bank Demerara, and Crane, West Coast Demerara.
The Head of State cautioned the Project Engineer from the Housing and Water Ministry, Thakur Persaud, that delinquency would not be tolerated and that there would be no further extensions for the completion of the highway.
“You’re not going past April for this, y’all know that, right?” President Ali indicated on Saturday.

In September 2022, some $11.8 billion in contracts were signed for the construction of the Schoonord-to- Crane four-lane highway – a project that is part of a much larger initiative to establish a secondary road link to Parika, East Bank Essequibo (EBE).
The works included two roundabouts, 11 reinforced concrete box culverts, 36 pre-stressed bridges, and road signage and markings. The project was awarded to eight contractors – VR Construction Inc, Avinash Contracting & Scrap Metal Inc, L-Heureuse Construction and Services Inc, GuyAmerica Construction Inc, AJM Enterprise, Vals Construction, Puran Bros Disposal Inc, and JS Guyana Inc.
All contractors were required to finish their respective projects by October 25, 2023. However, after massive delays, they were given an extension.
During Saturday’s site visit, the Guyanese Leader told the project engineer to ensure that liquidated damages are sought from the contractors over the extension given.













