…pipeline installation progressing
ExxonMobil is on track to deliver gas to Guyana’s shore by the end of the year, as the laying of the pipeline continues to progress satisfactorily.
Installation of the pipeline forms part of the transformative gas-to-energy project, in which are also included an Integrated Natural Gas Liquid (NGL) plant and a 300-megawatt (MW) combined cycle power plant to be situated at Wales, West Bank Demerara (WBD). The Guyana Government has envisioned startup of this project by 2025, thus realising its commitment to deliver cleaner, cheaper, and more reliable energy to the population.

While the Government is working with a number of partners to establish the NGL and the power plant components, ExxonMobil is responsible for executing the laying of the pipeline.
“…all the way from connections we’ve talked about on the FPSOs, the risers, the deepwater pipeline; all the way up onto the shallow shelf, crossing the seawall, and then all the way down to Wales for the onshore pipeline,” President of ExxonMobil Guyana, Alistair Routledge, told a press conference on Tuesday.
“At that point, it passes over to the Government, who is responsible for the integrated plant for the NGL extraction and the power generation, and then the tie in to the national grid,” he explained.
The onshore portion of the pipeline installation is about 40 per cent completed, while the offshore component is about 55 per cent completed.
“Last year, we had installation campaigns in two parts: we had the ultra-shallow piece, which are mud flaps at low tide…we did about 18 kilometres. So, we executed a good portion of that…then we also installed in the shallow water…going from that 18-kilometre mark out to where the shelf drops down into the deep water,” Routledge outlined.












