…contractor demanded additional $513.3M 1 day after new Govt took office
…project delays continue despite 317 days’ extension
After repeated breaches by a contractor, protracted delays and almost tripling of the contract costs, the Government has terminated a $356.8 million contract that was awarded to Chung’s Global Enterprise to construct the headquarters of the Health Ministry.
In a letter seen by this publication, Attorney General Anil Nandlall wrote to Cleon Chung of Chung’s Global Enterprise and informed him that the contract was being terminated effective October 31, 2020, on the grounds of contractual breaches.