CJIA expansion project…
…President flays all parties for disastrous project
…tells CHEC to fix it and stick to original contract
By Lakhram Bhagirat
Former Public Infrastructure Minister, David Patterson and the project team overseeing the ongoing Cheddi Jagan International Airport (CJIA) expansion project took the decision not to penalise contractor China Harbour Engineering Company (CHEC) for delays, according to the current Project Manager Carissa Gooding.

Gooding made the disclosure while being grilled by President Dr Irfaan Ali during his site visit with Chinese Ambassador Cui Jaichun on Monday.
The President’s visit was prompted by the reports of never-ending issues plaguing the project coupled with the fact that the initial project completion date is well over a year past due.
It has been two years since the deadline for completion was slated for 2018. When the coalition Government came into power in 2015, the project was put on hold, but after discussions between Patterson and CHEC, it was later announced that the project would be continued but a number of downgrades were done to the design.

Some US$138 million of the allocated costs was funded by the EXIM (Export-Import) Bank of China while US$12 million was spent by the Guyana Government. It was not expected to surpass that sum but Guyana had to stand additional expenses.
President Ali said the visit with the Chinese Ambassador is to ensure that the Guyanese people and the Government get what was agreed upon in the original contract.
“Our intention is to get what was signed for. What was in the contract is what we have to get. The airport that was in the contract is what has to be delivered to the Government of Guyana and the people…We have major issues with the sewer system. The COVID-19 pandemic has given us some time to correct some of these things but there are major difficulties. The sewer system, from what I heard, is not functional because as soon as you use it, it has to be shut down. The system is not working. All of these are major issues that were raised by the airport authorities and the Ministry,” the President said.

Ali pointed out that under the initial contract, the airport was supposed to be extended to include a 17,000 square metres arrival/departure terminal building along with 8 boarding bridges but instead what was delivered was a rehabilitated terminal building with four boarding bridges. The rehabilitated terminal building is also plagued with construction and retrofitting issues.
Other issues with the project include the poor air conditioning, substandard materials, lack of equipment maintenance, flooding in sections of the airport, leaking roof, tiles falling out, glass on the boarding bridges cracking, and lampshades falling off, undersized extractor fans, fire alarm systems not functioning, damaged chairs in departure lounge and lack of spares, as-built drawings and operations and maintenance manuals among others.
“There is a lot of issues in terms of making even this facility operational but our major concern is getting back to the original contract and to the original agreement. If one is to look outside this airport, you would believe in any way shape or form these resources were spent on this airport,” Ali told stakeholders.
During his visit, the President held a meeting with the airport management, CHEC officials, the consultant and project manager. It was during the meeting that Gooding made a presentation detailing the issues with the expansion project and the failure of CHEC to address those.